Prime Residency 3 Construction Updates
- Home
- Prime Residency 3 Construction Updates
Construction Updates
Construction keeps progressing at Prime Residency 3 by Prescott at Al Furjan. We are happy to share the latest updates with our customers. In addition to the project progress pictures we shared, we also share the official progress report by DLD with the site inspection date. As construction advances, further details and reports will be updated for all our customers.
Activities Milestone
- Shuttering for Lift Machine Slab
- Plaster work at 7th floor
- Excavation for Boundary wall at elevation B
- Fire Sealant work at 6th floor
- Aluminium & Glass Work at 2nd, 3rd, 6th & 7th floor
- Aluminium Screen at elevation C
- Paint work at elevation A & C
- Kitchen cabinet work at 3rd floor
- Tiles work at 6th & 7th floor
- False ceiling work at 4th ,5th & 6th floor
- Wooden door work at 4th & 5th floor
- Wardrobe fixing at 1st, 2nd & 3rd floor
- Waterproof surface prep at 7th floor
- Light wiring at 7th floor
- Electrical 1st fix at 7th floor
- Meter dressing at 6th floor
- Video intercom at 7th floor
- Cable tray installation at ground floor
- Power & Data wiring at 6th floor
- Epoxy work preparation at podium 2
- Fire alarm and emergency work at 6th & 7th floor
- DB dressing at 1st floor
- Drainage high level at P2
- Fire Fighting pump room & ground floor
- FAD at 6th & 7th floor
- CHW at 5th floor