Construction Updates

Construction keeps progressing at Prime Residency 3 by Prescott at Al Furjan. We are happy to share the latest updates with our customers. In addition to the project progress pictures we shared, we also share the official progress report by DLD with the site inspection date.

As construction advances, further details and reports will be updated for all our customers.

 

*Q3 2022 Construction Progress

Last updated: 1st May 2023

Activities Milestone

✓ Steel Work on 6th to 7th Floor Core Wall
✓ Steel Work on the 7th Floor (Part 2)Slab
✓ Shuttering Work for the 7th Floor (Part 2) Slab
✓ Block Work at the 4th Floor (Part 3)
✓ Plaster Work at 3rd Floor (Part 2&3)

✓ Waterproofing Surface Preparation at 3F (Part1 Kitchen & Toilet)
✓ Painting Work at 1F (Mockup Flat) Wall
✓ Tiles Work at 2F (Part 2 Toilet Wall)
✓Aluminum Frame Installation at 1st Floor Level
✓ False Ceiling Work at 1st Floor Mock Up Room


✓PPR Pipe Fixing at 2nd and 3rd Floor
✓ LPG Work at 2nd Floor & Podium 2
✓AC Work at 1st Floor
✓ Fire Fighting Pipe fixing at 1F
✓ Video Intercom, Data & Light Wiring at 2nd Floor
✓ Slab Containment at the 7th Floor