Construction keeps progressing at Prime Gardens by Prescott at Arjan. We are happy to share the latest updates with our customers. In addition to the project progress pictures we shared, we also share the official progress report by DLD with the site inspection date.
As construction advances, further details and reports will be updated for all our customers.
*Q3 2023 Construction Progress
Previous
Next
Activities Milestone
Boundary wall footing is still in progress at UG
Trilateral shifting work is in progress on the 1st floor.
Handrail Glass U Channel Installation work is in progress on 2nd floor.
Elevation 1 side stone fixing is in progress on the 1st to 6th floor.
Elevation 2 & 3 sides Plaster work and apply Bitumen paint work is in progress 1st to 5th floor.
High-level closing work is in progress on 2nd floor.
Balcony waterproofing work is in progress on ad floor.
Plumbing -Fixing floor trap end to cap & corridor PPR fixing works/HVAC-Duct insulation and installation at 6th floor.
Wet area wall tile installation work is in progress at 4th floor.
Dry area floor tile installation and nib closing work is in progress at itel & 5th floor.
Paintwork and sleeve grouting work is in progress on 5th floor.
Plaster work is in progress at 6th floor.
Electrician-Wall conducting in flat No102/Plumbing A/C drain pipe fixing work in progress 1st floor
Plumbing -A/C drain pipe fixing work/Electrician- megger testing work is in progress at 2nd floor.
Electrician- Tray trunking work in electrical room & light wire pulling /Plumbing – Fixing floor trap end to cap & fixing water heater /HVAC-Pressure testing work is in progress at ad , 4th & 5th floor.